Formosa 1 (Phase 2) Offshore Wind Farm

Taiwan

Jan De Nul – Formosa 1 (Phase 2) Offshore Wind Farm – January 2019 to October 2019 - 17 Array and 3 Export Cables  Correll Services was delighted that Jan De Nul selected our company to complete the termination & testing on the first major offshore wind farm in…

Read more

66kV Pre-Qualification Termination & Jointing Activities

Japan and South Korea

Seaway Offshore Contractors – 66kV Pre-Qualification Termination & Jointing Activities – June 2019 to February 2020  CS was engaged by SOC to carry out the installation of four different manufacturers HV products being considered for use on a…

Read more

Inner Hebridean Islands

Inner Hebridean Islands

Briggs Marine – Inner Hebridean Islands, Scotland – January 2020 to March 2020 – 1 Subsea to Land Cable  CS contracted with Briggs Marine to complete cable jointing and testing works on the subsea cables and land cables between islands.  The works include:  Fabrication of…

Read more

Changhua Demonstration (TPC) Offshore Wind Farm

Singapore

Jan De Nul – Changhua Demonstration (TPC) Offshore Wind Farm – November 2019 to October 2021 – 23 Array & 4 Export Cables  Following the successful delivery of the Formosa 1 (phase 2) OWF in Taiwan, CS was delighted that Jan De Nul once again chose our…

Read more

Kincardine Floating Offshore Wind Farm (Phase 2)

North Sea, Aberdeen Coast

Global Marine Systems – Kincardine Floating Offshore Wind Farm (Phase 2) – July 2020 to September 2021 – 1 Subsea Export Cable & 5 Array Cables  Correll Services are delighted to be working with Global Marine Systems again to complete…

Read more