Prysmian – Neart Na Gaoithe OWF – July 2022 to October 2022 – 220kV Export Cable Pull-in, Termination & Testing
Correll Cable Installation & Power Services Division were delighted that Prysmian awarded our organisation the Cable Pull, Termination and Testing contract on Neart Na Gaoithe. We are very privileged to be involved in the Scottish Offshore Wind Farm . CIPS was responsible for:
- Pre-project meetings
- Creation of RAMS
- Post Lay Testing (continuity, insulation resistance, Time Domain Reflectometry and Optical Time Domain Reflectometry).
- On the offshore assets:
- On the offshore assets:
- Cable pull of 2 x export cables on 2 x OSS platforms
- Supply Scaffolding for the support of the cable installation
- Stripping the export cables to expose the HV cores and FO cable
- Complete the permanent hang-off
- Route the HV and FO cable into GIS and Fibre Enclosure
- Cleat the HV cores from the hang-off to the GIS
- Terminate and splice the FO cable into the cabinet
- Assist in the termination of the three power cores into the GIS
- Complete post installation testing from the onshore substation to the offshore assets (IR, TDR & OTDR)
- Deliver an Inspection and Test Plan for the installed and tested system, forming part of key payment milestone.