Jan De Nul – Formosa 2 Offshore Wind Farm – January 2022 to September 2022 – 66kV Array & Export Cables

Correll Electrical Engineering (CEE) were delighted that Jan De Nul once again chose our company to complete the subsea cable termination & testing works on their 3rd contract Taiwan waters. The Formosa 2 project will be managed through our Taiwan Brach with the HQ in Taipei,  we shall be deploying our two local technicians onto the project throughout.

On the Formosa 2 project, Correll Services was responsible for:

  • Pre-project meetings
  • Site visits
  • Creation of RAMS
  • Mock-up trials at Switchgear and TP manufacturers facilities in Indonesia.
  • Creation of quality documentation
  • Project HIRA meetings
  • Post Lay Testing (continuity, insulation resistance, Time Domain Reflectometry and Optical Time Domain Reflectometry).
  • Onshore export cable stripping and routing
  • Onshore export jointing of the HV & FO cables

On the offshore assets:

  • Stripping the export cables to expose the HV cores and FO cable
  • Stripping the array cables to expose the HV cores and FO cable
  • Complete the permanent hang-off
  • Route the HV and FO cable into the TP/WTGS
  • Cleat the HV cores from the hang-off to the GIS
  • Terminate and splice the FO cable into the cabinet
  • Terminate three power cores into the GIS
  • Complete post installation testing from the onshore substation to the offshore assets (VLF, IR, TDR & OTDR)
  • Deliver an Inspection and Test Plan for the installed and tested system, forming part of key payment milestone.