Jan De Nul – Formosa 1 (Phase 2) Offshore Wind Farm – January 2019 to October 201917 Array and 3 Export Cables 

Correll Services was delighted that Jan De Nul selected our company to complete the termination & testing on the first major offshore wind farm in waters around Taiwan On the project, CS was responsible for: 

  • Pre-project meetings 
  • Site visits 
  • Creations of RAMS 
  • Creation of quality documentation 
  • Project HIRA meetings 
  • Mock-up trials at TP manufacturers facility in Thailand 
  • Post Lay Testing (continuity, IR, TDR & OTDR). 
  • Onshore export cable stripping and routing 
  • Onshore export jointing of the HV & FO cables 
  • Onshore substation HV & FO cable routing, cleating and termination 
  • On the 22 offshore assets: 
    • Stripping the export cable to expose the HV cores and FO cable 
    • Stripping the array cables to expose the HV cores and FO cable 
    • Complete the permanent hangoff 
    • Route the HV and FO cable into the TP/WTGS 
    • Cleat the HV cores from hangoff to the GIS  
    • Terminate and splice the FO cable into the cabinet 
    • Terminate three power cores into the GIS 
    • Complete post installation testing from the onshore substation to the offshore assets (VLF, IR, TDR & OTDR) 
    • Deliver an Inspection and Test Plan for the installed and tested system, forming part of key payment milestone. 