Jan De Nul – Formosa 1 (Phase 2) Offshore Wind Farm – January 2019 to October 2019 – 17 Array and 3 Export Cables
Correll Services was delighted that Jan De Nul selected our company to complete the termination & testing on the first major offshore wind farm in waters around Taiwan. On the project, CS was responsible for:
- Pre-project meetings
- Site visits
- Creations of RAMS
- Creation of quality documentation
- Project HIRA meetings
- Mock-up trials at TP manufacturers facility in Thailand
- Post Lay Testing (continuity, IR, TDR & OTDR).
- Onshore export cable stripping and routing
- Onshore export jointing of the HV & FO cables
- Onshore substation HV & FO cable routing, cleating and termination
- On the 22 offshore assets:
- Stripping the export cable to expose the HV cores and FO cable
- Stripping the array cables to expose the HV cores and FO cable
- Complete the permanent hang–off
- Route the HV and FO cable into the TP/WTGS
- Cleat the HV cores from hang–off to the GIS
- Terminate and splice the FO cable into the cabinet
- Terminate three power cores into the GIS
- Complete post installation testing from the onshore substation to the offshore assets (VLF, IR, TDR & OTDR)
- Deliver an Inspection and Test Plan for the installed and tested system, forming part of key payment milestone.