  • Global Offshore – Block Island OWF Cable Repair

Global Offshore – Block Island OWF Cable Repair – August 2020 to Present – 1 Export Subsea Cable

Global Offshore approached CS to support them with HV and FO services associated with the Block Island cable repair/replacement project in the USAThis is the second contract for Correll Services in the USA associated to OWF’s cable repairs. We are responsible for the Jointing & Testing of the Export cables between Land and the Wind Turbine Generator, including: 

  • Mobilising 6 Technicians and 1 Offshore Installation Manager 
  • Pre-project meetings 
  • Site visits (jointing habitat)  
  • Creations of RAMS 
  • Creation of quality documentation 
  • Project HIRA meetings 
  • Load-out Testing 
  • Post Lay Testing (continuity, insulation resistance, Time Domain Reflectometry and Optical Time Domain Reflectometry). 
  • On the offshore CLV & assets: 
    • Cutting of existing Export cable 
    • Stripping the Export cables to expose the HV cores and FO cable 
    • Complete the 33kV Power CSL subsea Joint. 
    • Deliver an Inspection and Test Plan for the installed and tested system, forming part of key payment milestone. 